Intel says an explosion at its Fab 28 facility near Kiryat Gat, Israel, led to a shutdown of about two weeks. The company expects the disruption to cost about $600 million in lost revenue over two quarters and affect server processor shipments in Q4 2026 and Q1 2027.
Intel says an explosion at its Fab 28 facility near Kiryat Gat, Israel, forced the plant to stop operations for about two weeks, and the company expects the disruption to result in approximately $600 million in lost revenue over two quarters. The shutdown is expected to affect server processor shipments in the fourth quarter of 2026 and first quarter of 2027.
Intel Chief Financial Officer Dave Zinsner described the shutdown during the company’s earnings call. He said the facility had been closed for about two weeks and that Intel expected production to resume by the end of that week. His comments indicate a planned restart, not confirmation that full output had already returned.
The disruption is expected to affect server processors made with Intel’s 10nm-class process technologies. Intel expects lower shipments in both Q4 2026 and Q1 2027, with the resulting lost revenue estimated at about $600 million across the two-quarter period. The estimate concerns lost revenue; no separate figure for repair costs or other expenses was provided.
The reported incident took place earlier in the month at Fab 28 near Kiryat Gat. The available account does not detail the explosion’s cause, the extent of damage, or whether anyone was injured. The facility’s production stoppage and Intel’s revenue estimate are the central confirmed business impacts disclosed in the earnings-call remarks.
Intel Fab 28 · Business Impact Brief
Explosion Triggers Two-Week Shutdown at Intel’s Fab 28
Intel expects about $600 million in lost revenue over two quarters, with lower server processor shipments in Q4 2026 and Q1 2027. A planned restart is not confirmation of full production recovery.
What the shutdown means
Fab 28 makes server processors used in data centers and enterprise systems. Intel expects fewer shipments in two consecutive quarters, though it has not quantified customer-level effects or identified specific models and orders.
A facility-level disruption
The disclosed impact centers on server processors made with Intel’s 10nm-class process technologies. Intel has not said all manufacturing or all processor shipments stopped.
Tighter supply is possible
Customers and equipment makers may need to plan around reduced availability or changed delivery schedules. Intel has not described the impact by customer.
Lost revenue estimate
The $600 million figure is lost revenue, not a stated profit reduction. Intel has not explained the calculation or whether the estimate may change.
Shutdown to shipment impact
Intel described a planned production restart, while shipment effects are expected to continue into early 2027. The company has not provided a detailed ramp-up schedule.
Explosion reported
The incident occurred at Fab 28 near Kiryat Gat, Israel.
Plant shut down
Operations were halted following the incident.
Production to resume
Zinsner expected production to start up by the end of the earnings-call week.
Shipments affected
Intel expects lower server processor shipments across both quarters.
Two quarters in view
Intel expects reduced server processor shipments in both periods. The illustration below marks the reported timeframe; Intel has not published quarter-by-quarter volume estimates.
Disruption may outlast the stoppage
A two-week halt can affect shipments beyond the shutdown itself. Intel has not said how quickly output will return to expected levels, so the restart date alone does not establish full recovery.
What remains unknown
Intel’s disclosed account provides a business impact estimate and a planned restart window, but leaves key incident and recovery details open.
Cause and damage
The cause of the explosion, the extent of physical damage, and whether anyone was injured have not been detailed.
Actual output ramp
The expected restart is not confirmation that production resumed or that Fab 28 returned to normal output.
Specific orders affected
No customer-by-customer assessment, processor model list, or detailed recovery schedule has been provided.
Updates on Fab 28’s operating status, the pace of production recovery, Q4 2026 and Q1 2027 shipment expectations, and any revision to the lost-revenue estimate.
Key questions
What happened at Fab 28?
An explosion at Intel’s facility near Kiryat Gat, Israel, led to a shutdown of about two weeks, according to CFO Dave Zinsner.
How much revenue could be lost?
Intel estimates about $600 million in lost revenue over two quarters. This is not a disclosed profit impact.
Which products are expected to be affected?
Server processors made with Intel’s 10nm-class process technologies, with lower shipments expected in Q4 2026 and Q1 2027.
Has production restarted?
Zinsner said Intel expected production to start up again by the end of that week. The available information does not confirm a restart or full output.
Server Chip Shipments Face Delays
A two-quarter production impact matters because Fab 28 makes server processors, products used in data centers and enterprise systems. Intel expects fewer shipments during two consecutive quarters, so customers and equipment makers may need to account for tighter availability or altered delivery schedules. The company has not quantified customer-level effects.
The $600 million estimate gives investors a measure of the financial impact Intel currently associates with the shutdown. It is a lost-revenue estimate, not a stated reduction in profit, and the information does not explain how Intel calculated it or whether the estimate could change as production returns.
Products Worth Considering

Sonos Era 100 SL Compact, Microphone-Free Speaker – Black

Logitech MX Keys S Wireless Keyboard, Graphite

LG UltraGear 27-Inch QHD OLED Gaming Monitor, 240Hz, 0.03ms, G-SYNC Compatible, FreeSync Premium Pro, HDMI 2.1
As an affiliate, we earn on qualifying purchases.
Fab 28 and Intel’s Production Timeline
Fab 28 is an Intel manufacturing facility in southern Israel, near Kiryat Gat. The reported disruption centers on server processors produced using Intel’s 10nm-class technology, rather than a general claim that all Intel manufacturing or all processor shipments were halted.
The timeline disclosed so far is limited: the explosion occurred earlier in October 2026, the facility was shut for about two weeks, and Intel’s CFO said the company expected to begin production again by the end of the earnings-call week. Intel also expects shipment effects to extend into early 2027. No detailed production-recovery schedule was provided.
Damage and Recovery Details Remain Unknown
Intel has not publicly detailed what caused the explosion, how much physical damage occurred, or whether the incident caused injuries. The information disclosed also does not specify which server processor models or customer orders will be most affected.
The expected restart date is not the same as a return to normal production. Intel has not provided a ramp-up schedule or said how quickly output will recover. The $600 million figure is an estimate, and the company has not explained whether that number may change as operations restart and shipments are reassessed.
Watch for Production and Shipment Updates
The next key development is whether Intel restarts production on the schedule Zinsner described and how quickly the facility returns to expected output. Updates on Fab 28’s operating status would help clarify whether the initial two-week stoppage has longer production consequences.
Investors and customers will also be watching for further detail on the Q4 2026 and Q1 2027 shipment outlook, including any revision to the lost-revenue estimate. Intel has not given a more detailed timetable or customer-by-customer assessment in the information currently available.
Source: Tom’s Hardware
Key Questions
What happened at Intel’s Fab 28?
An explosion at the facility near Kiryat Gat, Israel, led Intel to shut the plant for about two weeks, according to comments by CFO Dave Zinsner.
How much does Intel expect the shutdown to cost?
Intel expects about $600 million in lost revenue over two quarters. The figure is an estimate and refers to lost revenue, not a disclosed profit impact.
Which Intel products are expected to be affected?
The disruption is expected to affect server processors made using Intel’s 10nm-class process technologies. Intel expects lower shipments in Q4 2026 and Q1 2027.
Has production at Fab 28 restarted?
Zinsner said Intel expected production to start up again by the end of the week of the earnings call. The information available does not confirm that production actually resumed or that the facility returned to full output.
Source: Tom’s Hardware